Feasibility Study Migros Altstetten

Location Zurich-Altstetten

Programme Existing building:
Refurbishment underground parking and ground floor - 2nd floor; retail, gastronomy
Extension above existing building:
2nd - 4th floor offices and technology
5th - 16th floor three residential towers, 17th floor technology
Green spaces:
Roof garden on existing building and city park on unbuilt site area

Feasibility Study 2020 – 2021, 1st Phase
2022 – 2023, 2nd Phase

Commission Genossenschaft Migros Zurich

Gross Floor Area 78‘188 m2

Team GG Mike Guyer, 1st Phase: Damien Andenmatten, Alois Merkt, 2nd Phase: Michèle Favre, Dylan Kreuzer, Stefan Thommen

Landscape Architecture Studio Vulkan Landschaftsarchitektur AG, Zurich (2nd Phase)

Structural Engineer WaltGalmarini AG, Zurich (2nd Phase)

Building Services Engineer Concept-G AG, Winterthur (2nd Phase)

Acoustical Engineer Kuster und Partner AG, Zurich (2nd Phase)

Photos Gigon/Guyer